Tiered Bridge South Round, Talavera

Innovative support system with Megaprop "W" props that carries the load of the full width of the deck (36m) up to centered supports in the foundations of the 2 central temporary piles, thus minimizing the need for foundations in the Tagus River bed.

Bridge of the Third Millennium, Zaragoza

Structure of shoring towers and Megaprop porticoed formwork support system made up of Superslim and T200 beams, for the execution of the Arch of the Third Millennium Bridge, which served as the entrance to the Universal Expo in Zaragoza. With a length of 246 m., it is a World Record for Cable-stayed Arch Concrete Bridge.

El Bosque Bridge, Colombia

Multiple porticoed structure of standard RMDK profiles, supported on Megaprop towers and Load Scaffolding for drawer section bridge. Allows transit through a triple mixed gantry during the execution of the upper deck. Formwork structure with Superslim and T200 beams.

Bridge over the Guadalfeo River, Granada

Kwistage curdled and porticoed formwork with R700 trusses for spans of up to 40 m.

Bridge over the Ozama River, Santo Domingo, Dominican R.

Support beam on pylons with Megatrus lattice and formwork with Superslim beams and wooden beams.

Vía Rápida Camara de Lobos, Madeira, Portugal

Example of a combination of different solutions for a portico support system. With Megaprop towers that, depending on the span, support RMDK standard profiles or R700 trusses, for the support of a box deck with longitudinal slopes and variable transverse camber, using a formwork boat structure with Superslim and T200 beams and double bottom.

Viaduct Basagoiti, Mondragon

"V" pile formwork made up of Superslim and T200 beams. Shoring system made up of R700 trusses and Megaprop towers.

Vto. Palacios, LAV Madrid- Galicia Tr. Cernadilla- Pedralba

Kwikstage shoring system to support formwork boats made up of Superslim and T200 beams for the construction of a viaduct with a box section. This is an economic and high-performance system for the construction of bridges and viaducts of medium height when the support terrain has the appropriate load capacity.

Hyperronda of Malaga

Megaprop structure suspended in a pile for in situ execution of the upper lintel.

Viaduct of Portos, Orense

Climbing formwork for stacks of up to 70 m. high with a feed rate of 5 m. per laying.